The latest possible dates an activity can start and finish without pushing back the project completion date.
Late Start (LS) and Late Finish (LF) are backward-pass CPM calculations that determine the latest possible date an activity can begin and still allow the project to complete on time. LS and LF define the outer boundary of the scheduling window for each activity. The difference between late dates and early dates equals total float for that activity.
Late dates define how much an activity can slip before it threatens the contract completion date, so they are the backbone of float calculation and critical-path identification that estimators rely on to sequence subs and stage cash flow. Understanding late dates also strengthens a contractor's position in delay claims, since they prove which activities had no slack when an owner-caused disruption hit.
A scheduler reads an activity's late finish to confirm a long-lead steel package can still be ordered two weeks later without delaying the project's substantial completion.
Get AI-powered bid alerts, automated form filling, and proposal drafting.
Start Free Trial