Skip to main content
Data Reference

Predecessor

March 2026Quick referenceConstructionBids.ai
Back to Glossary

Quick Answer

Scheduling

A task that must be completed before the next task can start.

Definition

A predecessor is an activity that must begin or finish before another activity (the successor) can begin or finish, as defined by the logical relationships in a CPM schedule. The four relationship types are Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF). Correct predecessor logic is fundamental to a valid CPM schedule.

Why It Matters in Bidding

Predecessor logic determines what is on the critical path, which directly affects the project duration an estimator prices into general conditions and time-related overhead. Sloppy or missing predecessors produce an unrealistic schedule that understates the time and money needed, exposing the bidder to liquidated damages and cash-flow strain. In delay claims, the defensibility of the schedule turns on whether predecessor relationships reflect how the work actually had to be built.

Example

Building the bid schedule, the estimator sets slab-on-grade as a finish-to-start predecessor to interior framing, so the CPM correctly shows that any concrete delay pushes framing and lengthens the time-related general conditions in the bid.

Related Terms

Questions Contractors Ask

What are the four predecessor relationship types in a CPM schedule?

Finish-to-Start, where the predecessor must finish before the successor starts, is most common. Start-to-Start ties two activities' starts together, Finish-to-Finish ties their completions, and Start-to-Finish is rare and links a predecessor's start to a successor's finish. Choosing the right type keeps the schedule logic realistic and the critical path accurate.

How do predecessors affect the critical path?

The critical path is the longest chain of dependent activities with no float, and predecessors define that chain. If a critical predecessor slips, every downstream successor shifts and the completion date moves. Estimators and schedulers use predecessor logic to find which activities drive duration and where added crews or sequencing could shorten the job.

What is the difference between a predecessor and a successor?

A predecessor is the controlling activity that must start or finish first; the successor is the activity that depends on it and follows according to the relationship type and any lag. Every logical tie has both. Reversing or omitting these links produces open ends that invalidate the schedule and weaken any later delay analysis.

Need more than definitions?

Get AI-powered bid alerts, automated form filling, and proposal drafting.

Start Free Trial

Complete your stack with public & government bids.

ConstructionBids.ai fills the public-procurement gap with official source links, matching, alerts, risk review, and bid-decision workflow.

7-day free trialCancel anytime12,500+ verified sources