This glossary is educational workflow guidance. Verify contract, licensing, lien, wage, bonding, insurance, and procurement questions with the issuing agency or qualified counsel.
630 terms found
1-12 of 630
...
Browse all 630 terms A–Z
A
- Accounts Payable
- Accounts Receivable
- ACI (American Concrete Institute)
- Acoustical Ceiling
- ADA (Americans with Disabilities Act)
- Addendum
- Additional Insured
- Additive Alternate
- Admixture
- AGC (Associated General Contractors)
- Aggregate
- AIA (American Institute of Architects)
- AIA Contract
- Air Entrainment
- Air Handler
- AISC (American Institute of Steel Construction)
- Allowance
- Alternates
- Ampere (Amp)
- ANSI (American National Standards Institute)
- Arbitration
- Arc Fault Circuit Interrupter (AFCI)
- As-Built Drawings
- ASHRAE
- Asphalt
- Assignment
- ASTM
B
- Back Charge
- Backcharge
- Backfill
- Backflow Preventer
- Ballast
- Base Bid
- Baseboard
- Baseline Schedule
- Batch Plant
- Batt Insulation
- Beam
- Bearing Wall
- Bent
- Bid
- Bid Bond
- Bid Day
- Bid Documents
- Bid Form
- Bid Guarantee
- Bid Leveling
- Bid Opening
- Bid Package
- Bid Peddling
- Bid Protest
- Bid Rigging
- Bid Security
- Bid Shopping
- Bid Tabulation
- Bidder
- Bidding Documents
- Billing
- BIM (Building Information Modeling)
- Blanket Policy
- Board Foot
- BOD (Basis of Design)
- Boiler
- Bond Claim
- Bonding Capacity
- Borrow Pit
- Bracing
- Branch Circuit
- Breach of Contract
- Breaker Panel
- BTU
- Budget Estimate
- Builder's Risk Insurance
- Building Automation System
- Building Code
- Building Drain
- Building Information Modeling (BIM)
- Building Permit
- Building Sewer
- Built-Up Roof (BUR)
- Bull Float
- Bullnose
- Bus Bar
C
- Cable Tray
- CAGE Code
- Cantilever
- Cap Sheet
- Cash Flow
- Cast Iron
- Caulk
- Ceiling Grid
- Cement
- Ceramic Tile
- Certificate of Insurance
- Certificate of Occupancy
- Certificate of Substantial Completion
- Change Directive
- Change Order
- Chase
- Chilled Water System
- Chiller
- Circuit
- Circuit Breaker
- Cladding
- Claim
- Claimant
- Cleanout
- Closeout
- Closet Flange
- CMAR (Construction Manager at Risk)
- CMU (Concrete Masonry Unit)
- Coil
- Column
- Commercial General Liability (CGL)
- Commissioning
- Compaction
- Competent Person
- Competitive Bidding
- Completed Operations Coverage
- Composite Material
- Compressive Strength
- Compressor
- Conceptual Estimate
- Concrete
- Concrete Masonry Unit
- Concrete Pump
- Concrete Slab
- Concurrent Delay
- Condensing Unit
- Conditions of the Contract
- Conductor
- Conduit
- Confined Space
- Consent of Surety
- Consolidation
- Construction Administration
- Construction Lien
- Construction Manager
- Construction Manager at Risk
- Construction Trust Fund
- Contingency
- Contract
- Contract Documents
- Contract Sum
- Contractor
- Contractual Obligations
- Control Joint
- Cooling Tower
- Copper Piping
- COR (Change Order Request)
- Cost Code
- Cost Engineer
- Cost Estimate
- Cost Overrun
- Cost Plus Contract
- Cost to Complete
- Counterflashing
- CPM (Critical Path Method)
- Crew Hour
- Cricket
- Critical Path
- Critical Path Method (CPM)
- Cross-Connection
- Crown Molding
- CSI (Construction Specifications Institute)
- CSI MasterFormat
- Cubic Yard
- Curing
- Cut and Fill
D
- Daily Report
- Damper
- Davis-Bacon Wages
- DB (Design-Build)
- DBB (Design-Bid-Build)
- DBE (Disadvantaged Business Enterprise)
- Dead Load
- Deductive Alternate
- Deep Foundation
- Default
- Delay Claim
- Delay Damages
- Design Development
- Design Phase
- Design-Bid-Build
- Design-Build
- Detailed Estimate
- Dewatering
- Diaphragm
- Diffuser
- Dimensional Lumber
- Direct Costs
- Disconnect
- Dispute Resolution
- Document Control
- Domestic Water
- DOT (Department of Transportation)
- Dowel
- Drain-Waste-Vent (DWV)
- Draw Request
- Drawings
- Drip Edge
- Drywall
- Ductwork
- Duration
E
- Each
- Early Start / Early Finish
- Earned Value
- Earthwork
- Eave
- Economizer
- Electrical Panel
- Engineered Wood
- EPA (Environmental Protection Agency)
- EPDM
- Epoxy Floor
- Erosion Control
- Errors and Omissions (E&O)
- Estimate
- Estimator
- Evaporator
- Excavation
- Excavation Safety
- Excess Liability
- Exculpatory Clause
- Exhaust Fan
- Expansion Joint
- Exposed Aggregate
F
- Fall Arrest System
- Fall Protection
- Fan Coil Unit
- Fascia
- Fast-Tracking
- Fastener
- Feeder
- FF&E (Furniture, Fixtures, and Equipment)
- Fiber Cement
- Fiberglass
- Field Order
- Fill Material
- Final Completion
- Final Estimate
- Final Inspection
- Final Lien Waiver
- Fine Grading
- Finish Grade
- Fire Resistance Rating
- Fire Watch
- Fire-Rated Assembly
- First Aid
- Fixture Unit
- Flashing
- Flatwork
- Float
- Flooring
- Flow Rate
- Fly Ash
- Foam Insulation
- Footing
- Force Majeure
- Form
- Formwork
- Foundation
- French Drain
- Front-End Loading
- Front-Loading
G
- Galvanized Steel
- Gantt Chart
- Gas Piping
- GC (General Contractor)
- GC Markup
- General Aggregate
- General Conditions
- General Conditions (Contract)
- General Conditions Cost
- General Contractor
- Geotextile
- Girder
- Glazing
- GMP (Guaranteed Maximum Price)
- Grade Beam
- Grading
- Gravel
- Ground Fault Circuit Interrupter (GFCI)
- Grounding
- Grout
- Guaranteed Maximum Price
- Guardrail System
- Gypsum Board
H
I
L
- Labor Burden
- Lag
- Laminate
- Laminated Veneer Lumber
- Land Clearing
- Late Start / Late Finish
- Lateral Force
- Lateral Load
- Lavatory
- Lean Construction
- LEED (Leadership in Energy and Environmental Design)
- Lessons Learned
- Letter of Intent
- Liability Insurance
- Lien
- Lien Claimant
- Lien Priority
- Lien Release
- Lien Waiver
- Linear Foot
- Lintel
- Liquidated Damages
- Live Load
- Load Center
- Load-Bearing Wall
- Lockout/Tagout (LOTO)
- Look-Ahead Schedule
- Loss Payee
- Low Voltage
- Lump Sum
- LVT (Luxury Vinyl Tile)
M
- Main Shutoff Valve
- Makeup Air Unit
- Man-Hour
- Markup
- Masonry Unit
- Mass Excavation
- Material Safety Data Sheet (MSDS/SDS)
- Material Takeoff
- Mechanic's Lien
- Mediation
- Membrane
- MEP (Mechanical, Electrical, Plumbing)
- Metal Stud
- Meter
- Milestone
- Miller Act
- Millwork
- Mini-Split
- Mobilization Cost
- Modification
- Modified Bitumen
- Moment Connection
- Moment Frame
- Mortar
- Mud Slab
- MWBE (Minority/Women-Owned Business Enterprise)
N
O
P
- P-Trap
- Packaged Unit
- Paint
- Parametric Estimate
- Parapet
- Partial Lien Waiver
- Pay-If-Paid
- Pay-When-Paid
- Payment Application
- Payment Bond
- PCO (Potential Change Order)
- Per Occurrence Limit
- Performance Bond
- Personal Protective Equipment (PPE)
- PEX Tubing
- Phasing
- Pier
- Pile
- Pitch
- Plywood
- Polyvinyl Chloride
- Porcelain Tile
- Portland Cement
- Post-Tensioning
- Pound Per Square Inch (PSI)
- Pre-Bid Conference
- Pre-Stressed Concrete
- Precast
- Precast Concrete
- Preconstruction
- Predecessor
- Preliminary Notice
- Prequalification
- Pressure Regulator
- Pressure Treated Lumber
- Prevailing Wage
- Prime Contractor
- Primer
- Professional Liability
- Profit
- Progress Billing
- Progress Payment
- Project Closeout
- Project Delivery Method
- Project Engineer
- Project Manager
- Project Manual
- Prompt Payment Act
- Proposal
- Pull Planning
- Punch List
- Purlin
R
- Raceway
- Rafter
- Ready-Mix Concrete
- Rebar
- Receptacle
- Refrigerant
- Reinforcement
- Request for Proposal
- Request for Qualifications
- Resource Leveling
- Responsible Bidder
- Responsive Bidder
- Retainage
- Retainage Release
- Retaining Wall
- Retention
- RFI (Request for Information)
- RFP (Request for Proposals)
- RFQ (Request for Qualifications)
- Ridge
- Rigid Insulation
- Riprap
- Roofing Square
- Rooftop Unit
- Rough Grading
- Rough Order of Magnitude
- Rough-In
S
- Safety Data Sheet (SDS)
- Sanitary Sewer
- Scaffold Safety
- Schedule Acceleration
- Schedule Compression
- Schedule of Values
- Scope of Work
- Screed
- SDVOSB (Service-Disabled Veteran-Owned Small Business)
- Sealant
- Sealed Bid
- Sediment Control
- Seismic Design
- Service Entrance
- Shear Wall
- Sheathing
- Sheet Metal
- Sheet Piling
- Shingle
- Shop Drawing
- Shop Drawings
- Shoring
- Silica Exposure
- Silt Fence
- Single-Ply Membrane
- Site Preparation
- Site Safety Plan
- Site Superintendent
- Site Visit
- Slab-on-Grade
- Slump Test
- Snap Tie
- Soffit
- Softwood
- Soil Boring
- Soil Compaction Test
- Soil Pipe
- Soil Stabilization
- Sole Source
- SOV (Schedule of Values)
- Span
- Specification
- Specifications
- Specifications Document
- Split System
- Spoil
- Square (roofing)
- Square Foot
- Square Foot Estimate
- Square Yard
- Standing Seam
- Steel
- Stop Notice
- Stored Materials
- Structural Insulated Panel
- Structural Steel
- Stucco
- Subcontract
- Subcontractor Bid
- Subcontractor Default Insurance (SDI)
- Subgrade
- Submittal
- Substantial Completion
- Substitution
- Substrate
- Successor
- Sump Pump
- Supplementary Conditions
- Supply Line
- Surety
- Surety Bond
- Survey
- Swale
- Switchgear
T
- Take-Off
- TCO (Temporary Certificate of Occupancy)
- Termination for Cause
- Termination for Convenience
- Terrazzo
- Thermoplastic Polyolefin (TPO)
- Thermostat
- Three-Week Look-Ahead
- TI (Tenant Improvement)
- Tie Beam
- Tilt-Up
- Time Impact Analysis (TIA)
- Ton (material)
- Ton (mechanical)
- Toolbox Talk
- Topsoil
- Transformer
- Trap Primer
- Treated Lumber
- Trench Safety
- Trenching
- Trim
- Trowel Finish
- Truss
- Turnover
U
V
W
- W-Shape
- Wainscoting
- Walk-Through
- Wallboard
- Warranty
- Waste Pipe
- Water Closet
- Water Hammer
- Water Heater
- Water-Cement Ratio
- Waterproofing Membrane
- Watt
- WBS (Work Breakdown Structure)
- Weather Delay
- Wind Load
- Wire Gauge
- Work in Progress (WIP)
- Workers' Compensation
- WOSB (Women-Owned Small Business)
- Wrap-Up Insurance (OCIP/CCIP)
Explore More Resources
Frequently Asked Questions
This glossary contains 630+ construction terms organized across 19 categories, from estimating and bidding to lien law and safety.
This glossary is designed for construction professionals at all levels, from apprentices learning industry terminology to experienced contractors who encounter unfamiliar terms in contracts, specifications, or regulatory documents.
Terms are organized into 19 categories: Estimating & Bidding, Contracts & Legal, Materials & Specifications, Structural, Mechanical / HVAC, and more. You can filter by category or browse A-Z.
These definitions provide general industry-standard meanings. However, contract terms should always be interpreted according to the specific contract language, applicable law, and any project-specific definitions. Consult a construction attorney for legal interpretation.
Yes. If you notice a term missing from our glossary, contact us through the support widget and we will review it for inclusion.
