The earliest possible dates an activity can start and finish based on when all prior tasks are done.
Early Start (ES) and Early Finish (EF) are forward-pass CPM calculations that determine the earliest possible date an activity can begin and the earliest possible date it can be completed, given its predecessors and durations. ES is calculated as the maximum EF of all predecessors plus any lag. EF equals ES plus duration minus one. These dates define the boundaries within which work can be scheduled without delaying successors.
Early Start and Early Finish from the forward pass establish how soon work can begin and finish, which lets estimators sequence trades, time material procurement, and plan cash flow against the schedule submitted with the bid. Knowing the early dates also reveals which activities have float versus those on the critical path, informing where to commit resources and where schedule risk truly lives.
After building the bid schedule, an estimator runs the forward pass and sees the electrical rough-in has an Early Start two weeks before the owner's required completion, giving the team float to absorb a possible material delivery delay.
Get AI-powered bid alerts, automated form filling, and proposal drafting.
Start Free Trial