The upfront cost of getting equipment, workers, and facilities set up at a new job site.
Mobilization cost is the expense a contractor incurs to set up construction operations at a project site, including transporting equipment and materials, establishing temporary facilities, hiring and relocating personnel, and obtaining required permits. Mobilization is typically billed as a percentage of the contract in the first pay application. Demobilization covers the cost of removing equipment and closing out the site at project completion.
Because mobilization is one of the few line items billed in the first pay application before significant work is in place, it directly drives a contractor's early cash flow and is a common vehicle for front-loading a schedule of values. Owners and lenders scrutinize mobilization percentages, and many public contracts cap mobilization at a set percentage of the contract to prevent contractors from being overpaid early relative to actual progress.
The contractor billed $180,000 for mobilization in the first pay application to cover crane transport, trailers, and site fencing, but the owner's mobilization clause limited the line to 5 percent of the contract value.
Get AI-powered bid alerts, automated form filling, and proposal drafting.
Start Free Trial