Change orders are inevitable on construction projects. On public works contracts, change order management requires understanding specific procedures, documentation requirements, and pricing methods that differ from private work. Proper change order management protects your profitability and maintains good agency relationships.

Understanding Public Works Change Orders

Change orders modify the original contract scope, price, or time.

Types of Changes

1. Directed Changes

  • Owner-initiated scope additions
  • Design changes by architect/engineer
  • Third-party requirement changes
  • Code or regulation changes

2. Constructive Changes

  • Differing site conditions
  • Defective specifications
  • Impossibility of performance
  • Owner acceleration orders

3. Cardinal Changes

  • Changes outside contract scope
  • May constitute breach
  • Rare but important to recognize

Change Order vs. Change Directive

| Document | Description | Pricing | |----------|-------------|---------| | Change Order | Agreed modification | Price agreed before work | | Change Directive | Disputed change | Price determined later | | Field Order | Minor adjustment | Within contingency |

Public Works Change Order Procedures

Government contracts have specific procedural requirements.

Typical Process Flow

  1. Change identification - Need for change recognized
  2. Change request - Formal request submitted
  3. Impact assessment - Contractor evaluates impact
  4. Proposal submission - Cost and time proposal
  5. Negotiation - Price and terms discussed
  6. Approval - Required approvals obtained
  7. Execution - Change order signed
  8. Implementation - Work performed

Required Approvals

Public works changes often require multiple approvals:

  • Project manager/resident engineer
  • Contracting officer
  • Legal review (for significant changes)
  • Governing body (above certain thresholds)
  • Federal approval (if federally funded)

Threshold Examples:

| Authority Level | Typical Threshold | |-----------------|-------------------| | Project manager | Up to $25,000 | | Contracting officer | $25,000 - $100,000 | | Agency head | $100,000 - $500,000 | | Governing body | Above $500,000 |

Pricing Change Orders

Accurate pricing is critical for change order profitability.

Pricing Methods

1. Lump Sum

  • Agreed price before work
  • Preferred by owners
  • Requires accurate estimating
  • Risk on contractor

2. Unit Prices

  • Pre-established rates
  • Quantities adjusted as-built
  • Common for quantity variations
  • Less risk than lump sum

3. Time and Materials (T&M)

  • Actual costs plus markup
  • Requires detailed documentation
  • Used when scope unclear
  • Risk on owner

4. Cost Plus Fixed Fee

  • Actual costs tracked
  • Fixed fee for overhead/profit
  • Common on federal contracts
  • Detailed record-keeping required

Cost Components

All pricing methods should include:

Direct Costs:

  • Labor (including burden)
  • Materials
  • Equipment
  • Subcontractor costs

Indirect Costs:

  • Supervision
  • Temporary facilities
  • Small tools
  • Job overhead extension

Markup:

  • Overhead (typically 10-15%)
  • Profit (typically 5-10%)

Public Works Markup Limitations

Many agencies limit markups:

| Component | Typical Maximum | |-----------|-----------------| | Contractor overhead and profit | 15% | | Subcontractor overhead and profit | 10% | | Self-performed work | 15% combined |

Federal Contracts (FAR):

  • No set percentages but "fair and reasonable"
  • Combined O&P typically 15-25%
  • Tiered limits for subs

Documentation Requirements

Thorough documentation supports change order claims.

Essential Records

Daily Documentation:

  • Daily reports with change-related activities
  • Time sheets by task
  • Equipment logs
  • Material delivery tickets
  • Photos and videos

Cost Records:

  • Labor costs with burden calculations
  • Material invoices
  • Equipment rental agreements
  • Subcontractor billings

Correspondence:

  • RFIs related to change
  • Submittals affected
  • Meeting minutes
  • Emails and letters

T&M Documentation

Time and materials work requires:

Daily T&M Tickets:

  • Date and location
  • Description of work
  • Workers by name and classification
  • Hours per worker
  • Equipment used
  • Materials installed

Signature Requirements:

  • Contractor foreman signature
  • Owner representative signature
  • Daily submission and verification

Force Account Procedures

Some agencies require force account documentation:

Force Account Process:

  1. Notify owner before starting work
  2. Track costs separately
  3. Submit daily tickets
  4. Obtain daily signatures
  5. Reconcile weekly
  6. Submit for payment

Differing Site Conditions

DSC claims are common on public works projects.

Type I: Conditions Differ from Contract

Conditions differ from those indicated in contract documents:

  • Subsurface conditions
  • Hidden existing conditions
  • Utilities not shown on plans

Required Documentation:

  • Pre-bid site investigation
  • Contract document references
  • Actual conditions encountered
  • Photos/videos of conditions
  • Contemporaneous notification

Type II: Unknown Physical Conditions

Conditions differ from those ordinarily encountered:

  • Unusual for type of work
  • Unusual for geographic area
  • Couldn't have been anticipated

Claim Elements:

  • Description of condition
  • Why it's unusual
  • Impact on work
  • Cost and time effects

DSC Claim Procedure

  1. Immediate notification - Before disturbing conditions
  2. Documentation - Thorough recording
  3. Preserve evidence - Don't disturb unnecessarily
  4. Written claim - Formal submission per contract
  5. Negotiate resolution - Work with owner

Time Extensions

Changes often require schedule adjustments.

Compensable vs. Non-Compensable Delays

| Type | Time Extension | Cost Recovery | |------|----------------|---------------| | Owner-caused | Yes | Yes | | Weather (excusable) | Yes | Usually No | | Contractor-caused | No | No | | Force majeure | Yes | Usually No |

Time Extension Requests

Include in your request:

  • Description of change/delay
  • Original schedule impact
  • As-built schedule impact
  • Net extension requested
  • Supporting schedule analysis

Schedule Analysis Methods

As-Planned vs. As-Built:

  • Compare original and actual schedules
  • Identify delay causes
  • Allocate responsibility

Time Impact Analysis:

  • Insert delay into schedule
  • Calculate forward impact
  • Preferred by many agencies

Window Analysis:

  • Analyze specific time periods
  • Contemporaneous approach
  • Good for complex projects

Disputes and Claims

When negotiations fail, formal claims may be necessary.

Claims Process

1. Contract Claims Procedure

  • Follow contract requirements exactly
  • Meet notice deadlines
  • Submit certified claims
  • Pursue administrative remedies

2. Federal Contract Disputes Act

  • Submit certified claim
  • Contracting officer decision
  • Appeal to boards of contract appeals
  • Court of Federal Claims option

3. State/Local Claims

  • Varies by jurisdiction
  • May require administrative hearing
  • Litigation if necessary

Preserving Claim Rights

Essential Actions:

  • Timely written notice
  • Document everything
  • Don't accept waiver language
  • Reserve rights in writing
  • Meet all deadlines

Certification Requirements

Federal claims over $100,000 require certification:

"I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable; and that I am authorized to certify the claim on behalf of the contractor."

Best Practices for Change Order Management

Proactive Management

  • Review documents thoroughly before bidding
  • Identify potential issues early
  • Track all potential changes
  • Communicate promptly with owner
  • Document continuously

Negotiation Strategies

  • Present well-documented proposals
  • Be reasonable but firm
  • Understand owner constraints
  • Focus on fair resolution
  • Maintain relationships

Common Mistakes to Avoid

  1. Missing notice deadlines - Follow contract requirements
  2. Poor documentation - Document everything contemporaneously
  3. Inadequate pricing - Capture all cost impacts
  4. Ignoring schedule impacts - Always evaluate time effects
  5. Waiving rights - Reserve claims in writing

Technology for Change Order Management

Document Management

  • Centralized document storage
  • Easy retrieval and searching
  • Version control
  • Access controls

Cost Tracking

  • Separate cost codes for changes
  • Real-time cost tracking
  • Automatic markup calculations
  • T&M ticket management

Schedule Software

  • Critical path analysis
  • Time impact evaluation
  • As-built recording
  • Delay analysis tools

Case Studies

Successful Change Order

Situation: Contractor discovered unmarked utilities during excavation.

Actions Taken:

  1. Stopped work immediately
  2. Notified owner in writing
  3. Photographed conditions
  4. Preserved evidence
  5. Tracked costs separately
  6. Submitted detailed proposal

Result: Full recovery of $180,000 in extra costs plus 15-day time extension.

Failed Change Order

Situation: Contractor encountered hard rock during trenching.

Issues:

  • No written notice until 3 weeks later
  • Continued work before owner inspection
  • No separate cost tracking
  • Verbal agreement not documented

Result: Claim denied due to late notice and lack of documentation.

Next Steps

Ready to improve your change order management?

  1. Review contract procedures - Understand requirements
  2. Implement documentation systems - Capture data in real-time
  3. Train field staff - Everyone should know procedures
  4. Establish pricing standards - Consistent approach
  5. Track all potential changes - Miss nothing

Related Articles

Frequently Asked Questions

What's the typical markup allowed on change orders? Most public agencies allow 10-15% combined overhead and profit for self-performed work, and 5-10% for subcontracted work. Check your specific contract.

How long do I have to submit a change order request? Contract-specific, but typically 7-21 days after becoming aware of the change. Meet the deadline or risk waiving your claim.

Can I refuse to do directed changes? Generally no. Most contracts include "changes" clauses requiring performance pending price resolution. Document your disagreement and proceed.

What if the owner won't approve a legitimate change? Document thoroughly, follow claims procedures, reserve rights, and pursue administrative remedies. Consult construction counsel if necessary.

How do I prove delay impacts on schedule? Use critical path analysis showing how the change affected project completion. Contemporaneous schedule updates and daily reports support your case.

ConstructionBids.ai LogoConstructionBids.ai

AI-powered construction bid discovery platform. Find government and private opportunities from 2,000+ sources across all 50 states.

support@constructionbids.ai

Disclaimer: ConstructionBids.ai aggregates publicly available bid information from government sources. While we strive to provide accurate and up-to-date information, we do not guarantee the accuracy, completeness, or timeliness of any bid data. Users should verify all information with the original source before making business decisions. ConstructionBids.ai is not affiliated with any government agency.

Data Sources: Bid opportunities are sourced from federal, state, county, and municipal government portals including but not limited to SAM.gov, state procurement websites, and local government bid boards. All data remains the property of the respective government entities.

© 2025 ConstructionBids.ai. All rights reserved.
Made in the USAPrivacyTerms