Quick answer
At a glance
OSHA's construction standards (29 CFR Part 1926) set triggers that cost money: fall protection at 6 feet, cave-in protection for most trenches 5 feet deep or more, and a competent person inspecting scaffolds before each shift. Public owners also check your OSHA 300 logs, EMR and citation history before they award.
Key takeaways
What you need to know
- Price fall protection from 6 feet (10 feet on scaffolds) and cave-in protection for trenches 5 feet deep or more.
- Owners set their own EMR and safety-score cutoffs, so read each prequalification form instead of assuming 1.00.
- The 2025 OSHA penalty amounts still apply: up to $16,550 for a serious violation and $165,514 for a willful or repeated one.
Ready to find bids that match your trade?
Thousands of verified public-bid sources. Cancel anytime.
The Part 1926 rules that change your price
Federal OSHA's construction standards are in 29 CFR Part 1926. Most of them shape the work plan, but a handful set hard triggers that turn straight into labor, equipment and supervision in your estimate.
| Rule | What it requires | Where it lands in the bid |
|---|---|---|
| 1926.501(b)(1) | An unprotected side or edge 6 feet or more above a lower level needs guardrails, a safety net or personal fall arrest | Guardrail, anchors and harnesses at roof edges, floor openings and leading edges, plus install and removal time |
| 1926.451(g)(1) | An employee on a scaffold more than 10 feet above a lower level must be protected from falling | Scaffold guardrails or fall arrest on every scaffold run over that height |
| 1926.451(f)(3) | A competent person inspects scaffolds for visible defects before each work shift and after anything that could affect their integrity | Daily inspection time by a qualified person, for as long as the scaffold stands |
| 1926.451(f)(7) | Scaffolds are erected, moved, dismantled or altered only under the supervision of a competent person | A supervisor on every scaffold change, not just the first erection |
| 1926.652(a)(1) | Each employee in an excavation is protected from cave-ins, unless it is entirely in stable rock, or under 5 feet deep with no sign of a cave-in on a competent person's examination | Sloping, shoring or a trench box for every trench run 5 feet or deeper |
| 1926.20(b) | The employer runs a safety program and has competent persons make frequent and regular inspections of the site, materials and equipment | Superintendent or safety staff time across the schedule |
| 1926.21(b)(2) | Each employee is instructed in recognizing and avoiding unsafe conditions | Orientation and training hours for every new worker on the job |
A "competent person" has a specific meaning under 1926.32(f): someone who can identify existing and predictable hazards and has the authority to take prompt corrective action. Naming one is not enough if that person cannot stop the work. See the competent person definition for how the term shows up in specifications.
Reading the drawings for safety cost
The triggers above are measurable from the bid documents, which is what makes them priceable:
- Fall exposure. Measure roof perimeter, slab edges, shafts and floor openings at or above 6 feet. Each linear foot needs a guardrail, a net or a tie-off plan.
- Excavation depth. Read the civil and utility profiles for every trench run that reaches 5 feet. Long runs at depth change your equipment list, not just your labor.
- Scaffold height and duration. Masonry, exterior finishes and high interior work often run on scaffold for weeks. Multiply the per-shift inspection by the shifts it stands.
- The owner's safety section. An owner's safety specification can add requirements beyond OSHA, such as a full-time safety manager, site-specific training or stricter tie-off rules. Price what the specification says, not just the regulation.
A written plan makes these choices visible before bid day. The site-specific safety plan generator gives you a starting structure to adapt to the project.
What owners check before award
Public owners screen bidders for safety before they look at price, usually in a prequalification questionnaire. Three records come up again and again.
OSHA 300 and 300A logs
The OSHA 300 log records work-related injuries and illnesses, and the 300A is the annual summary. Under 29 CFR 1904.32, the summary is posted from February 1 to April 30 of the following year, and a company executive certifies that they have examined the log. Under 1904.33, the log, the annual summary and the incident reports are kept for five years.
Small employers have a partial exemption. Under 1904.1, a company with 10 or fewer employees at all times during the last calendar year does not need to keep the records unless OSHA or the Bureau of Labor Statistics tells it to in writing, and the count covers the whole company. Every covered employer must still report a work-related fatality. Owners can ask for the logs anyway, so a small firm should know what it will submit instead.
Experience modification rate (EMR)
The EMR comes from your workers' compensation insurance, not from OSHA. NCCI describes the experience rating modification as a comparison of an employer's payroll and loss records, usually over the latest three years, with similar employers. A mod below 1.00 is a credit and above 1.00 is a debit. Your carrier states the rate in a letter, and that letter is what owners ask for.
What owners do with the number varies:
- California's Labor Commissioner model questionnaire asks for the EMR for each of the past three premium years, how often you hold documented safety meetings, and how many times Cal/OSHA or federal OSHA cited you for serious, willful or repeat violations in the last five years. It sets no EMR cutoff.
- The California State University's prequalification instructions require OSHA Forms 300 and 300A for the last three complete years and score a safety worksheet, with 25 points the minimum to qualify. A firm that does not qualify for an EMR enters 1.00.
- One CSU campus project (Cal Poly Humboldt RFP PW23-3) required an EMR of 1.00 or less, but only from subcontractors with fewer than ten employees and under 20,000 hours worked, and only for that project.
The lesson is to read each owner's form. An EMR cutoff is an owner's choice, not an OSHA rule. Our prequalification questionnaire guide covers the rest of the packet, and the prequalification requirements guide covers how owners use it.
Federal work: the responsibility determination
On federal contracts, the contracting officer has to find a bidder responsible before award. FAR 9.104-1 lists what that means. It includes a satisfactory performance record, a satisfactory record of integrity and business ethics, and the organization and controls to perform the work. Those controls explicitly include "safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors."
FAR Part 9 does not name OSHA logs or EMR. A low price can still lose to a nonresponsibility finding, though, and a solicitation can add safety evaluation factors of its own.
What a citation can cost
OSHA's maximum penalties are adjusted for inflation each year, but the Department of Labor cancelled the 2026 adjustment, and the 2025 amounts still apply. They are written into 29 CFR 1903.15(d):
| Violation | Penalty |
|---|---|
| Serious | Up to $16,550 |
| Other-than-serious | Up to $16,550 |
| Willful | $11,823 to $165,514 |
| Repeated | Up to $165,514 |
| Failure to abate | Up to $16,550 per day |
A citation is more than the fine, though. Questionnaires like California's ask about serious, willful and repeat citations over five years, so one bad inspection can follow you into the next several prequalifications.
State-plan states
Some states run their own OSHA-approved programs. 29 CFR Part 1952 lists 22 state plans that cover both private-sector and state and local government workers (21 states and Puerto Rico), and 7 that cover only state and local government employees: Connecticut, New York, New Jersey, the Virgin Islands, Illinois, Maine and Massachusetts.
Part 1952 approves these plans for the enforcement of state standards. On a job in a full state-plan state, such as California, Washington, Michigan or Virginia, the state program's own standards apply to the site. Under DOL's penalty rule, a state plan's maximum and minimum penalties must be at least as effective as federal OSHA's. Check the state program's rules before you price a job in a state you don't usually work in.
A pre-bid safety checklist
| Check | Source |
|---|---|
| Fall exposures at 6 feet and scaffold work over 10 feet, measured from the drawings | 29 CFR 1926.501, 1926.451 |
| Trench runs 5 feet or deeper, and the protective system for each | 29 CFR 1926.652 |
| Who your competent persons are for excavation and scaffolds, and their time | 29 CFR 1926.32(f), 1926.451(f) |
| Three years of OSHA 300/300A logs, or your basis for the small-employer exemption | 29 CFR 1904.1, 1904.32, 1904.33 |
| Your EMR letter from the carrier, and the owner's cutoff if it has one | The owner's prequalification form |
| Citation history for the period the owner asks about | The owner's prequalification form |
| The owner's safety specification, and anything it adds beyond OSHA | The solicitation |
| The state's own plan, if the job is in a state-plan state | 29 CFR Part 1952 |
Sources
- 29 CFR 1926.501, fall protection, 1926.451, scaffolds, 1926.652, excavations, 1926.20, 1926.21 and 1926.32, via Cornell LII
- 29 CFR 1904.1, 1904.32 and 1904.33, recordkeeping
- 29 CFR 1903.15, penalty amounts; DOL's 2025 penalty adjustment and cancelled 2026 adjustment in the Federal Register
- 29 CFR Part 1952, approved state plans
- FAR 9.104-1, general standards of responsibility
- NCCI, ABCs of Experience Rating
- California DIR, Labor Commissioner's model prequalification questionnaire
- The California State University, prequalification instruction guide
- Cal Poly Humboldt, RFP PW23-3 subcontractor prequalification questionnaire
All sources were read on October 28, 2026.
FAQ
Frequently Asked Questions
At what height does OSHA require fall protection on a construction site?
In general construction work, 29 CFR 1926.501(b)(1) requires protection at an unprotected side or edge 6 feet or more above a lower level, using guardrails, safety nets or personal fall arrest systems. Scaffolds have their own trigger: 1926.451(g)(1) requires fall protection for employees more than 10 feet above a lower level.
Do small contractors have to keep OSHA 300 logs?
Under 29 CFR 1904.1, a company with 10 or fewer employees at all times during the last calendar year does not need to keep the injury and illness records, unless OSHA or the Bureau of Labor Statistics tells it in writing to. The count covers the whole company, and every covered employer must still report a work-related fatality to OSHA. Owners can still ask for the logs at prequalification.
Do public owners require an EMR below 1.00?
Some do, but it is set owner by owner and sometimes project by project. California's model prequalification questionnaire asks for three years of EMR without setting a cutoff, while one CSU campus project required 1.00 or less only from small subcontractors. Read the questionnaire for each bid.
How much can an OSHA citation cost in 2026?
The Department of Labor cancelled the 2026 inflation adjustment, so the 2025 amounts still apply: up to $16,550 for a serious violation, $11,823 to $165,514 for a willful one, up to $165,514 for a repeated one, and up to $16,550 per day for failure to abate.
Can a safety record affect a federal contract award?
Yes. Under FAR 9.104-1, the contracting officer must find a bidder responsible before award. The standard includes a satisfactory performance record and the organization and controls to perform, including safety programs for the work of the contractor and its subcontractors.