Guaranteed Maximum Price (GMP) contracts are increasingly common in construction, offering owners cost certainty while allowing contractors flexibility in means and methods. Understanding how GMP works helps you price appropriately and manage projects profitably.
What Is a GMP Contract
Definition
A Guaranteed Maximum Price contract establishes a ceiling price for construction work. The contractor guarantees the project won't exceed this price, absorbing any overruns while typically sharing any savings with the owner.
Key Components
GMP Amount
- Maximum owner will pay
- Includes all costs plus fee
- Established before or during construction
- Basis for payment and risk
Cost of Work
- Actual costs reimbursed
- Subcontractor costs
- Materials and equipment
- Direct labor
- General conditions
Contractor's Fee
- Fixed amount or percentage
- Compensation for services
- Not at risk (typically)
- Separate from contingency
Contingency
- Reserve for unknowns
- Part of GMP
- Usage controlled
- May share remaining
Basic Formula
GMP = Cost of Work + Contractor's Fee + Contingency
Owner Pays: Actual Cost of Work + Fee
(up to GMP maximum)
How GMP Differs from Other Contracts
vs. Lump Sum
Lump Sum
- Fixed price for defined scope
- No cost visibility to owner
- No savings sharing
- Complete documents typically
GMP
- Maximum with actual cost billing
- Owner sees costs
- Savings sharing possible
- Can start with incomplete documents
vs. Cost Plus
Cost Plus
- All costs reimbursed
- No price ceiling
- Owner bears all risk
- Maximum flexibility
GMP
- Costs reimbursed up to cap
- Price ceiling protects owner
- Contractor shares overrun risk
- Balanced approach
When GMP Is Used
Common Applications
Appropriate For
- Design still developing
- Fast-track projects
- Complex scope
- Collaborative relationships
- Owner wants cost visibility
Less Appropriate For
- Complete documents available
- Simple, well-defined scope
- Price-only selection
- Adversarial relationships
Typical Delivery Methods
Construction Manager at Risk
- GMP most common
- CM engaged during design
- Provides preconstruction services
- Establishes GMP before construction
Design-Build
- GMP sometimes used
- Progressive design-build
- Criteria-based selection
- GMP at design milestone
Establishing the GMP
Timing
When Set
- After sufficient design
- Typically 50-75% documents
- Before major construction
- Allows informed pricing
Too Early Risks
- High contingency needed
- More risk assumed
- Less accurate pricing
- Potential for disputes
Too Late Issues
- Loses benefit of early pricing
- Owner commitment delayed
- May miss cost targets
- Schedule pressure
Basis of GMP
Documents Required
- Drawings (percentage complete)
- Specifications (as developed)
- Design narrative/criteria
- Assumptions documented
- Exclusions listed
- Clarifications noted
Pricing Components
- Subcontractor pricing (competitive)
- Self-perform estimates
- General conditions
- Fee
- Contingency
GMP Proposal
Contents
- GMP amount
- Documents used as basis
- Assumptions and clarifications
- Exclusions
- Contingency amount
- Fee structure
- Schedule
Contingency Management
Purpose
What Contingency Covers
- Unforeseen conditions
- Design development
- Coordination issues
- Minor scope gaps
- Estimating variance
What It Doesn't Cover
- Owner changes
- Differing site conditions
- Design errors
- Scope additions
Sizing Contingency
Factors Considered
- Document completeness
- Project complexity
- Design firm track record
- Site conditions knowledge
- Historical experience
Typical Ranges
- 75% documents: 5-10%
- 50% documents: 8-15%
- Schematic: 15-25%
- Conceptual: Not advisable
Usage Control
Common Approaches
- Contractor-controlled (within limits)
- Owner approval required
- Joint approval
- Documented usage log
Tracking
- Log every use
- Justify each draw
- Forecast remaining
- Report regularly
Savings Sharing
Common Structures
- 50/50 split of remaining contingency
- Graduated sharing (more to contractor for more savings)
- Owner takes all (less common)
- Contractor takes all (rare)
Calculation Timing
- At project completion
- After punch list
- After warranty period (sometimes)
- Per contract terms
Risk Allocation
Contractor Risks
Under GMP
- Cost overruns above GMP
- Productivity issues
- Subcontractor performance
- Coordination problems
- Most field conditions
Mitigated By
- Adequate contingency
- Good estimating
- Strong management
- Quality subcontractors
Owner Risks
Under GMP
- Owner-directed changes
- Design errors (often)
- Unforeseen conditions (per contract)
- Schedule acceleration
- Owner-caused delays
Shared Areas
Negotiated Items
- Design development scope
- Allowance overruns
- Material escalation
- Permit costs
- Utility issues
Pricing Strategies
GMP Proposal Development
Key Considerations
- Document status and risk
- Subcontractor market
- Project complexity
- Owner relationship
- Competition level
Pricing Process
- Comprehensive estimate
- Risk analysis
- Contingency determination
- Fee calculation
- GMP assembly
Fee Structures
Common Approaches
- Fixed fee (most common)
- Percentage of cost (less common)
- Hybrid structures
- Performance incentives
Fee Protection
- Fee typically not at risk
- Earned regardless of outcome
- May be reduced for contractor default
- Separate from contingency
Competitive Considerations
If Competing for GMP Work
- Fee often comparison basis
- Contingency may be visible
- Total GMP matters
- Qualification important
Project Execution
Cost Tracking
Requirements
- Actual cost documentation
- Subcontract tracking
- Change order management
- Contingency log
- Regular reporting
Systems
- Job cost accounting
- Subcontract management
- Change tracking
- Document control
Open Book Approach
What It Means
- Owner sees actual costs
- Subcontract pricing visible
- No markup hidden
- Transparency required
Implications
- Accounting must be clean
- Documentation thorough
- Pricing defensible
- Trust essential
Change Management
Within GMP
- Contingency usage
- Scope clarification
- Design development
- No additional cost to owner
GMP Amendments
- Owner-directed changes
- Scope additions
- Differing conditions
- Documented adjustment
Common Issues
GMP Busts
When GMP Is Exceeded
- Contractor absorbs overage
- May negotiate with owner
- Claims possible if owner-caused
- Relationship damage likely
Prevention
- Adequate contingency
- Thorough estimating
- Strong management
- Early problem identification
Contingency Disputes
Common Conflicts
- What contingency covers
- Who approves usage
- Design development scope
- Savings sharing calculation
Resolution
- Clear contract language
- Documentation
- Regular communication
- Joint tracking
Scope Creep
Risk
- Design development exceeds expectations
- Contractor absorbs under GMP
- Disputes about what's included
Prevention
- Clear assumptions in GMP
- Design freeze expectations
- Regular scope alignment
- Change documentation
Conclusion
GMP contracts balance owner cost certainty with contractor flexibility. Success requires thorough estimating, appropriate contingency, disciplined management, and clear communication.
The key is understanding what risks you're assuming and pricing accordingly. Adequate contingency protects against foreseeable issues, while clear documentation of assumptions protects against scope disputes.
When executed well, GMP projects can be profitable for contractors while delivering owner satisfaction—a foundation for repeat relationships and ongoing work.
ConstructionBids.ai displays contract type information for opportunities, helping you identify GMP projects and understand risk allocation.