Construction Estimating Process: Complete Guide for Accurate Bids
Mastering the construction estimating process is fundamental to winning profitable projects and sustaining a successful contracting business. Accurate estimates enable competitive bidding while protecting your margins; inaccurate estimates cost you jobs or your profitability.
According to Procore and The Balance SMB research, estimating errors cause 50-70% of construction project losses. Whether you underbid and lose money or overbid and lose the job, poor estimating directly threatens business viability. The good news? Following a systematic estimating process dramatically improves accuracy and consistency.
This comprehensive guide walks through each phase of professional construction estimating, from initial document review through final bid assembly. Whether you're a general contractor, subcontractor, or specialty trade, these proven techniques will improve your estimating quality and win rate.
Phase 1: Document Review and Project Understanding
Effective estimating begins before you calculate a single cost. Thoroughly understanding project requirements prevents costly omissions and incorrect assumptions.
Essential Document Review Steps:
1. Collect Complete Documentation
Ensure you have the complete bid package before starting:
Architectural, structural, mechanical, electrical, and plumbing plans
Project specifications (all divisions)
All addenda and clarifications
Geotechnical reports and site surveys
Contract terms and general conditions
Insurance and bonding requirements
Prevailing wage determinations (if applicable)
Missing documents lead to scope gaps that surface after bid opening when it's too late to adjust pricing.
2. Attend Pre-Bid Conferences
Pre-bid meetings provide critical intelligence:
Owner priorities and evaluation criteria
Clarification of ambiguous requirements
Site access and logistics constraints
Project schedule and milestone requirements
Opportunities to meet potential partners or competitors
Information gathered at pre-bids often influences your bid strategy and pricing decisions.
3. Conduct Site Visits
Never bid a project without visiting the site when possible:
Verify existing conditions match plan assumptions
Assess access, laydown, and staging areas
Identify site challenges not apparent from drawings
Evaluate distances from material suppliers
Understand neighborhood impacts and restrictions
Site visits frequently reveal conditions that significantly impact costs and schedules.
4. Identify Risks and Clarifications Needed
During document review, note:
Specification conflicts or ambiguities
Unusual or unfamiliar requirements
Scope overlaps between trades
High-risk elements requiring contingencies
Questions requiring written clarification
Submit Request for Information (RFI) early to receive answers before your estimate is due. Implement strong construction document control best practices to track all project documents and updates.
Phase 2: Quantity Takeoffs
Quantity takeoffs form the foundation of accurate estimates. This phase requires systematic measurement of all materials, equipment, and labor required for your scope.
Takeoff Best Practices:
1. Organize by CSI Division or Trade
Structure your takeoff to match how you'll price the work:
Break the project into logical work packages
Follow CSI MasterFormat divisions for consistency
Create separate takeoff sheets for major systems or areas
Use standardized templates to ensure nothing is missed
2. Measure Systematically
Develop consistent measurement approaches:
Work from general to specific (building to room to detail)
Mark plans as you measure to avoid double-counting or omissions
Document your assumptions and measurement methods
Calculate waste factors based on material type and application
Cross-reference specifications while measuring
3. Leverage Digital Takeoff Software
Modern construction estimating software improves takeoff speed and accuracy:
On-screen measurement eliminates scale and calculation errors
Automatic area and volume calculations
Color coding shows completed versus remaining takeoff areas
Database linking to unit costs for instant pricing
Report generation for bid review and documentation
Popular options include Bluebeam, PlanSwift, and On-Screen Takeoff. Investment in quality software typically pays for itself on your first major estimate.
4. Review and Validate Quantities
Before pricing, verify your takeoff accuracy:
Compare quantities to similar past projects
Have a second estimator spot-check critical elements
Verify unit conversions and calculations
Ensure waste factors are included where appropriate
For detailed guidance on performing takeoffs, see the comprehensive tutorial on how to do construction takeoffs efficiently and accurately.
Phase 3: Pricing Labor, Materials, and Equipment
With accurate quantities established, the next phase applies current unit costs to develop your total direct costs.
Labor Pricing:
1. Determine Accurate Labor Rates
Your labor costs must reflect actual wages plus burdens:
Base wage rates for each classification
Payroll taxes (FICA, Medicare, unemployment)
Workers' compensation insurance
General liability insurance
Union benefits and fringes (if applicable)
Prevailing wage rates for public projects
Many contractors underprice labor by forgetting fully-burdened rates exceed base wages by 30-50%.
2. Apply Realistic Production Rates
Labor hours depend on productivity, which varies by:
Crew experience and skill levels
Project complexity and quality requirements
Site conditions and access constraints
Weather and seasonal factors
Learning curves on repetitive work
Use historical data from your completed projects to refine production rates. Industry databases (RS Means, Craftsman, etc.) provide starting points but should be adjusted for your actual performance.
Material Pricing:
1. Obtain Current Quotes
Material costs fluctuate, so price validity matters:
Request formal quotes from suppliers for major materials
Verify quotes are valid through your bid date
Confirm quantities match your takeoff
Include freight, delivery, and unloading costs
Add appropriate waste and damage factors
2. Consider Market Conditions
For projects with long lead times:
Factor potential price escalation
Identify long-lead items requiring early procurement
Consider material buyout strategies and pricing locks
Include escalation clauses in your bid if allowed
Equipment Costs:
Price both owned and rental equipment:
Owned equipment: hourly rates covering depreciation, maintenance, fuel
Rental equipment: market rates plus delivery and operator costs
Small tools and consumables: percentage allocation
Specialized equipment requiring subcontractors
Phase 4: Indirect Costs, Overhead, and Profit
Direct costs alone don't constitute a complete bid. Indirect costs, overhead, and profit must be calculated and added.
Indirect Project Costs:
Project management: Superintendent, project manager time
Site facilities: Temporary offices, utilities, sanitation
Safety program: Safety personnel, equipment, training
Quality control: Testing, inspections, documentation
Construction equipment: Cranes, hoists, scaffolding
Site logistics: Fencing, signs, security
Cleanup: Final cleaning and trash removal
Closeout: As-builts, warranties, owner training
General Overhead:
Allocate company overhead costs across all projects:
Office facilities and administrative staff
Estimating and business development
Accounting, legal, and professional services
Technology, software, and communications
Marketing and general business expenses
Calculate overhead as a percentage of direct costs based on annual company expenses divided by annual revenue volume.
Profit Margin:
Determine appropriate profit based on:
Project risk level (higher risk = higher profit requirement)
Market competitiveness (tighter markets = lower sustainable margins)
Owner relationship and repeat business potential
Current backlog and capacity availability
Strategic value of the project to your company
Profit margins typically range from 5% (competitive, low-risk) to 15%+ (higher risk or specialized work).
Phase 5: Bid Assembly and Review
The final phase compiles all estimate components into your formal bid submission.
Final Bid Assembly:
Compile all direct costs from your priced takeoffs
Add subcontractor quotes for work you're subcontracting (see subcontractor bid management strategies)
Include all indirect costs and project-specific expenses
Apply overhead percentage to cover company costs
Add profit margin appropriate to project risk and strategy
Include required bonds and insurance costs
Add contingency for identified risks (typically 2-5%)
Bid Review Process:
Before submission, conduct thorough review:
Verify all scope items are included
Check calculations and unit conversions
Confirm subcontractor quotes are complete and current
Review alternates and unit prices if required
Ensure compliance with all bid requirements
Have senior estimator or principal review final number
Continuous Improvement:
After bid submission, track results:
Record your bid amount and winning bid
Document estimating assumptions and risks identified
Compare estimates to actual costs on won projects
Refine production rates and unit costs based on actual performance
Share lessons learned across your estimating team
Using construction estimating software that integrates with your bid discovery process creates seamless workflow from opportunity identification through estimate completion.