Airport Construction Bidding Guide

December 19, 2025Updated October 29, 202611 min readConstructionBids.ai TeamReviewed by Haithum Abdelfattah, Founder & CEO
Back to Blog

At a glance

Most airport construction paid for with FAA Airport Improvement Program (AIP) grants is bid by sealed bid and awarded at a firm fixed price to the lowest responsive and responsible bidder. Above $250,000 the contract carries a 5% bid guarantee and 100% performance and payment bonds, and every bid needs a Buy American certificate and the DBE paperwork the solicitation asks for. Davis-Bacon wages apply over $2,000, and no work.

Key takeaways

  • AIP-funded airport construction is bid by sealed bid and awarded to the lowest responsive and responsible bidder unless the FAA approves another method.
  • Buy American certificates and the solicitation's DBE paperwork are responsiveness items on AIP bids.
  • The airport's CSPP is part of the specifications, and the contractor's SPCD must be approved before notice to proceed.

What you need to know

  • AIP sponsors use sealed bids by default. Competitive proposals need FAA approval and a written justification.
  • A bid without the Buy American certificate, or without the DBE documents the solicitation requires, can be rejected as nonresponsive.
  • The airport's Construction Safety and Phasing Plan becomes part of the specifications, and your Safety Plan Compliance Document must be approved before notice to proceed.

Ready to find bids that match your trade?

Thousands of verified public-bid sources. Cancel anytime.

Start 7-Day Free Trial

How AIP money reaches a construction contract

The Airport Improvement Program is a grant-in-aid program administered by the FAA. The grant goes to the airport sponsor, a public agency (or the private owner of a public-use airport) that applies to the FAA for an AIP grant, and the sponsor lets the construction contract.

Some states run part of the program. TxDOT's Aviation Division takes part in the FAA State Block Grant Program for general aviation airports, and MoDOT files its federally funded forms under a State Block Grant Program. Even when a state channels the money, the airport's own governing body can stay the sponsor: Alabama's aeronautics bureau says the local governing body remains the sponsor for all FAA-funded projects.

Expect time between bid opening and award. In Alabama's process, the sponsor submits its final AIP grant application after bids are received and the lowest responsive bidder is known. An older Wisconsin aeronautics program overview says the FAA requires grant applications for already-bid projects before July 1 of the construction year.

Sealed bids, the low bidder and FAA concurrence

On FAA Form 5100-131 (the sponsor certification for equipment and construction contracts, 2/24 edition), sponsors certify that their procurements follow the federal grant standards in 2 CFR 200.317 to 200.326. They may use state and local procedures if those conform. For the sealed-bid method, the sponsor certifies that the project was:

  • publicly advertised;
  • publicly opened at the time and place in the invitation for bids;
  • awarded as a firm fixed price contract to the lowest responsive and responsible bidder.

Sealed bidding is the preferred method. To use competitive proposals instead, the sponsor needs FAA approval and a written justification. The sponsor also gets FAA concurrence before award when only one qualified firm submits a responsive bid, when the award goes to anyone other than the lowest responsible bidder, or when life-cycle costing is a factor. Before awarding contracts and subcontracts over $25,000, the sponsor checks the System for Award Management for suspended or debarred firms.

State programs add their own steps. On Illinois's locally let projects at primary airports, the sponsor requests the FAA project manager's concurrence to award to the lowest responsive bidder, the bid package includes a bid proposal with the federal provisions and a schedule of prices, and the project is advertised for at least 30 days.

If you're new to these terms, see what makes a bidder responsive and how a sealed bid is opened and read.

Bonds

Above the simplified acquisition threshold, which the FAA form lists as $250,000, an AIP construction contract includes:

BondAmount
Bid guarantee5% of the bid
Performance bond100% of the contract price
Payment bond100% of the contract price

Sponsors print the same terms in their notices. The City of Rolla, Missouri's 2025 notice for an AIP project at Rolla National Airport asked for a 5% bid bond and separate performance and payment bonds, each equal to 100% of the contract price. Our performance bond requirements guide covers what a 100% performance bond obligates, and the bid bonds explainer covers the bid guarantee.

Buy American: the certificate goes in with the bid

AIP construction contracts carry the Buy American Preference in 49 U.S.C. 50101. The clause Wisconsin's aeronautics bureau put in its April 2026 federal requirements says federal funds may not be obligated unless all iron, steel and manufactured goods used in AIP-funded projects are produced in the United States, unless the FAA has issued a waiver, the item is excepted under FAR 25.108, or it is on the FAA's list of nationwide Buy American waivers.

The 2026 clause also has bidders certify, under Build America, Buy America, that construction materials used in the project are manufactured in the US. It defines those as articles made primarily of non-ferrous metals, plastic and polymer-based products (including PVC), glass, lumber or drywall. Items that are primarily iron or steel, manufactured products, cement and cementitious materials, and aggregates such as stone, sand or gravel are outside that definition.

What that means at bid time:

  • Missing certificate, rejected bid. The sponsor will reject as nonresponsive any bid that does not include a completed certification of compliance. The City of Rolla's 2025 notice used the same sentence.
  • Two certificate types. Projects for equipment or buildings use the certificate based on the total facility. Other projects, such as runway or roadway construction, use the certificate based on construction on the project.
  • Waivers have a deadline. A bidder that picks the waiver option on Wisconsin's Buy American agreement agrees, if it has the apparent low bid, to submit a formal waiver request within 15 calendar days of being selected as the responsive bidder, and not to seek a waiver after the contract is signed. The waiver types on the form include US components making up more than 60% of the cost of all components, and compliance raising the overall project cost by more than 25%.
  • Subcontracts are covered, and waivers are the prime's job. Buy American extends to all subcontracts on the project. Getting a waiver when one is needed is the prime contractor's responsibility, and cost increases from failing to get one aren't allowed.

Get supplier certifications for steel, electrical equipment and lighting before bid day, not after award.

Davis-Bacon wages and weekly payrolls

On AIP projects, construction and equipment installation contracts over $2,000 include the Davis-Bacon and Related Acts provisions (29 CFR part 5) and the Copeland Anti-Kickback Act. The bid solicitation includes the current federal wage rate schedules for the work classifications, so the rates you price are in the package. Under the contract clauses:

  • laborers and mechanics are paid unconditionally at least once a week;
  • the contractor submits a copy of all payrolls weekly for every week of work, through the sponsor to the FAA when the FAA isn't a party to the contract.

Our Davis-Bacon prevailing wage guide covers wage determinations, and the certified payroll guide covers the weekly reports.

DBE goals, prompt payment and the 2025 interim rule

Sponsors with an FAA DBE program include the clauses required by Title VI of the Civil Rights Act and 49 CFR Part 26 in all contracts and subcontracts. The contract assurance makes a failure to carry out those requirements a material breach. The remedies listed include withholding monthly progress payments and disqualifying the contractor from future bidding as non-responsible.

DBE paperwork is usually a responsiveness item:

  • Missouri, 2025. The City of Rolla's notice required bidders, as a condition of responsiveness, to submit the DBE firms' names, scopes, dollar amounts and confirmations, plus good faith efforts documentation if the goal wasn't met.
  • Wisconsin. Its advisory notice to bidders says that failing to include the required DBE documentation makes the bid non-responsive.

Once you're working, the prompt payment clause in Wisconsin's federal requirements has you pay each subcontractor within 10 days of receiving each payment from the sponsor, and return retainage within 10 days after the subcontractor's work is satisfactorily completed. The clause applies to DBE and non-DBE subcontractors alike. You can't terminate a DBE listed in your bid without the sponsor's prior written consent.

Certification is in flux. Under the DBE interim final rule published on October 3, 2025, firms certified using race- or sex-based presumptions must be reevaluated, with disadvantage shown case by case. Wisconsin has extended its recertification deadline to December 24, 2026. Confirm that your DBE partners are still certified before you list them. Concessions at airports fall under a separate program, the Airport Concession DBE program in 49 CFR Part 23.

For more on certification programs, see our guide to DBE, MBE and WBE requirements and the prompt payment guide.

The safety plan: CSPP and SPCD

Airfield work happens next to live operations, and the safety plan is part of the contract:

  • The airport's plan. The Construction Safety and Phasing Plan (CSPP) is the airport operator's overall plan for safety and phasing. It is included in the invitation for bids and becomes part of the project specifications.
  • Your document. The contractor prepares a Safety Plan Compliance Document (SPCD) that details how it will comply with the CSPP and with the current version of FAA Advisory Circular 150/5370-2. An Alaska DOT&PF plan from May 2026 says the advisory circular sets the format and content of both documents, and that both are enforceable parts of the contract.
  • No notice to proceed without it. Wisconsin's SPCD form says the notice to proceed can't be issued until the SPCD is approved, asks for it 14 days before the preconstruction conference, and requires a contact with 24-hour coverage for immediate response. Illinois requires a safety phasing plan approved by the FAA project manager before notice to proceed.
  • Only the winner submits it, but every bidder prices the plan. Wisconsin's notice says the SPCD is completed only by the contractor that is awarded the contract, and no deviation from the approved CSPP is allowed without the owner's or engineer's written approval.

Price the phasing the CSPP sets: work windows, closures, escorts, barricades and lighting.

The specifications: AC 150/5370-10

The FAA's construction standards can be part of the contract itself. Wisconsin's notice to bidders says that at primary air carrier airports (those with airline service), Advisory Circular 150/5370-10H, Standards for Specifying Construction of Airports, is part of the contract documents. General aviation airports in Wisconsin use the state's own 2021 standard specifications. MoDOT lists AC 150/5370-10 among the construction specifications for its federally funded projects.

The advisory circular also carries contract terms, not just technical items. Wisconsin's federal requirements point to its Section 80-09 for the owner's rights and remedies when it terminates a contract for the contractor's default.

Airport bid checklist

CheckWhere to find it
Is the project AIP-funded, and who is the sponsor?Advertisement, front end, grant references
Sealed bid or competitive proposal, and the award basisInvitation for bids, instructions to bidders
Bid guarantee, performance and payment bond amountsInstructions to bidders, contract forms
Which Buy American certificate applies, and supplier certificationsFederal provisions, Buy American forms
Wage rate schedules for your classificationsFederal provisions, wage determination
DBE goal, forms and deadline, and whether your DBEs are still certifiedDBE section, the certifying agency's directory
CSPP work windows, closures and escort rulesCSPP, phasing drawings
Badge, vehicle and security access requirementsSpecial provisions, airport security rules
Which edition of AC 150/5370-10 or the state specification governsSpecifications, notice to bidders

Sources

All sources were read on October 29, 2026.

Frequently Asked Questions

Do AIP-funded airport projects have to use sealed bids?

Sealed bidding is the preferred method. On FAA Form 5100-131, sponsors certify that sealed-bid procurements are publicly advertised, publicly opened, and awarded at a firm fixed price to the lowest responsive and responsible bidder. Using competitive proposals instead requires FAA approval and a written justification.

What bonds does an AIP construction contract require?

Contracts above the simplified acquisition threshold, which FAA Form 5100-131 lists as $250,000, include a 5% bid guarantee, a 100% performance bond and a 100% payment bond under 2 CFR 200.325.

Does Buy American apply to subcontractors on airport projects?

Yes. Wisconsin's advisory notice to bidders says the Buy American provision applies to all AIP-funded contracts and extends to all subcontracts. Its federal requirements make getting a waiver the prime contractor's responsibility, and cost increases from failing to get one are not allowed.

What is a Safety Plan Compliance Document (SPCD)?

It is the contractor's document describing how it will comply with the airport's Construction Safety and Phasing Plan (CSPP) and FAA Advisory Circular 150/5370-2. Both are enforceable parts of the contract, and in Wisconsin the notice to proceed can't be issued until the SPCD is approved.

Do Davis-Bacon wages apply to airport construction?

On AIP-funded projects, construction and equipment installation contracts over $2,000 include the Davis-Bacon and Related Acts provisions, and the bid solicitation includes the federal wage rate schedules. Contractors pay weekly and submit weekly certified payrolls.

Related Articles

Complete your stack with public & government bids.

ConstructionBids.ai fills the public-procurement gap with official source links, matching, alerts, risk review, and bid-decision workflow.

7-day free trialCancel anytimeThousands of verified sources