Back to Blog
Guides

Performance Bond Requirements for Construction: Complete Guide 2025

December 26, 2025
11 min read
CBConstructionBids.ai Team
Performance Bond Requirements for Construction: Complete Guide 2025

Performance bonds guarantee that contractors will complete projects according to contract terms. Understanding performance bond requirements is essential for contractors pursuing public works and many private construction projects.

What Is a Performance Bond?

A performance bond is a surety bond that guarantees the contractor will perform the contract according to its terms. If the contractor defaults, the surety is obligated to remedy the situation.

The Surety Relationship

Three parties are involved:

| Party | Role | Obligation | |-------|------|------------| | Principal | Contractor | Complete the contract | | Obligee | Owner | Protected against default | | Surety | Bond company | Guarantee performance |

How Performance Bonds Work

  1. Contractor obtains bond from surety
  2. Bond guarantees contract performance
  3. If contractor defaults, owner makes claim
  4. Surety investigates claim
  5. If valid, surety remedies default
  6. Surety seeks recovery from contractor

Performance Bond Requirements

When Performance Bonds Are Required

Mandatory (Miller Act):

  • Federal contracts over $150,000
  • 100% of contract value
  • Payment bond also required

State and Local:

  • Most public works projects
  • Typically over $25,000-$50,000 threshold
  • Amount varies by jurisdiction

Private Projects:

  • Often required by lenders
  • Large commercial projects
  • Project-specific requirements

Typical Bond Amounts

| Project Type | Performance Bond | Payment Bond | |--------------|------------------|--------------| | Federal | 100% of contract | 100% of contract | | State/Local | 100% of contract | 100% of contract | | Private | 50-100% of contract | 50-100% of contract |

Performance Bond vs. Payment Bond

Performance Bond:

  • Guarantees work completion
  • Protects owner from default
  • Covers completion costs

Payment Bond:

  • Guarantees payment to subs/suppliers
  • Protects unpaid parties
  • Prevents liens on project

Both are typically required together on public works.

Qualifying for Performance Bonds

Underwriting Criteria

Sureties evaluate contractors on the "Three C's":

1. Character

  • Business reputation
  • Personal integrity
  • Industry references
  • Credit history
  • Claims history

2. Capacity

  • Technical expertise
  • Project experience
  • Equipment and resources
  • Personnel capabilities
  • Backlog management

3. Capital

  • Financial strength
  • Working capital
  • Net worth
  • Bank relationships
  • Cash flow

Financial Requirements

Key Financial Metrics:

| Metric | Typical Requirement | |--------|---------------------| | Working capital | 10% of bond capacity | | Net worth | 10-15% of bond capacity | | Current ratio | Greater than 1.25 | | Debt to equity | Less than 3.0 |

Financial Statement Requirements:

  • CPA-prepared statements
  • Reviewed or audited (for larger limits)
  • Current (within 12 months)
  • Construction-specific format

Experience Requirements

Sureties look for:

  • Completed similar projects
  • Successful track record
  • Experienced key personnel
  • Relevant project references

Performance Bond Costs

Pricing Structure

Performance bonds are typically priced per $1,000 of contract value:

| Contract Amount | Rate Range | |-----------------|------------| | First $500K | $15-25 per $1,000 | | Next $2M | $10-20 per $1,000 | | Next $2.5M | $7-15 per $1,000 | | Next $2.5M | $5-10 per $1,000 | | Over $7.5M | $4-8 per $1,000 |

Rates vary significantly by contractor profile

Factors Affecting Rates

| Factor | Impact on Rate | |--------|----------------| | Financial strength | Higher strength = lower rates | | Experience | More experience = lower rates | | Project type | Complex projects = higher rates | | Claims history | No claims = lower rates | | Indemnity strength | Better indemnity = lower rates |

Example Cost Calculation

$5 Million Project:

| Tier | Amount | Rate | Premium | |------|--------|------|---------| | First $500K | $500,000 | $20/1000 | $10,000 | | Next $2M | $2,000,000 | $15/1000 | $30,000 | | Next $2.5M | $2,500,000 | $10/1000 | $25,000 | | Total | | | $65,000 |

This is 1.3% of contract value

Building Bonding Capacity

Capacity Calculation

Sureties typically calculate capacity as multiples of:

| Metric | Multiplier | Example | |--------|------------|---------| | Working capital | 10-15x | $500K WC = $5-7.5M capacity | | Net worth | 10-20x | $750K NW = $7.5-15M capacity |

Actual capacity is the lower of the two calculations.

Strategies to Increase Capacity

1. Strengthen Balance Sheet

  • Retain earnings in business
  • Minimize distributions
  • Build working capital
  • Reduce debt

2. Build Track Record

  • Complete projects successfully
  • Document performance
  • Maintain good references
  • Avoid claims and disputes

3. Develop Surety Relationship

  • Communicate regularly
  • Provide timely information
  • No surprises
  • Build trust over time

4. Professional Financial Statements

  • Use experienced construction CPA
  • Consider reviewed or audited statements
  • Provide comprehensive notes
  • Include proper schedules

Managing Work in Progress

Sureties monitor work-in-progress (WIP):

Key WIP Metrics:

  • Underbillings vs. overbillings
  • Backlog vs. capacity
  • Profit fade analysis
  • Cost to complete accuracy

Best Practices:

  • Accurate job costing
  • Timely billing
  • Proper revenue recognition
  • Regular WIP review

The Bonding Process

Getting Started

1. Find a Bond Producer

  • Construction-focused agent/broker
  • Strong surety relationships
  • Industry knowledge
  • Responsive service

2. Complete Application

Required Information:

  • Company history and structure
  • Owner background
  • Financial statements
  • Banking references
  • Project history
  • Current work in progress

3. Underwriting Review

  • Surety evaluates submission
  • May request additional information
  • Site visit possible
  • Interview with principals

4. Approval and Terms

  • Bonding line established
  • Single and aggregate limits
  • Rate schedule
  • Indemnity agreement

Obtaining Bonds for Specific Projects

Once approved:

  1. Request bond for specific project
  2. Provide contract and project details
  3. Surety reviews and approves
  4. Bond issued for submission

Surety Claims

When Claims Occur

Default triggers may include:

  • Failure to complete on schedule
  • Abandonment of work
  • Bankruptcy or insolvency
  • Failure to pay subcontractors
  • Failure to meet specifications

Claim Process

1. Owner Declares Default

  • Written notice to contractor
  • Opportunity to cure
  • Declaration of contractor default

2. Owner Makes Claim

  • Formal claim to surety
  • Documentation of default
  • Statement of damages

3. Surety Investigates

  • Reviews circumstances
  • Evaluates claim validity
  • Assesses options

4. Surety Response Options

  • Finance contractor completion
  • Take over and complete
  • Tender new contractor
  • Pay damages (up to bond amount)

Avoiding Claims

Best Practices:

  • Communicate problems early
  • Work with surety on solutions
  • Maintain adequate resources
  • Honor contract obligations
  • Document everything

Special Bonding Situations

Joint Venture Bonds

For JV projects:

  • Both partners may provide bonds
  • Proportional bonding possible
  • Cross-indemnification typical
  • Clear JV agreement needed

Subdivision Bonds

For development work:

  • Site improvement guarantees
  • Warranty bonds
  • Maintenance bonds
  • Often required by municipalities

Supply Bonds

For material supply contracts:

  • Guarantee delivery
  • Quality assurance
  • Less common than performance bonds

SBA Surety Bond Guarantee Program

The SBA helps small contractors obtain bonds.

Program Overview

  • Guarantees up to 90% of bond losses
  • Reduces surety risk
  • Enables bonds for marginal applicants
  • Available through approved sureties

Eligibility

  • Small business (SBA size standards)
  • Unable to obtain bonds otherwise
  • Contracts up to $6.5 million (standard)
  • Up to $10 million (federal)

How to Apply

  1. Work with SBA-approved surety or agent
  2. Apply through normal bonding process
  3. Surety requests SBA guarantee
  4. SBA reviews and approves

Working with Your Surety

Building a Strong Relationship

Communication Best Practices:

  • Regular financial updates
  • Project status reports
  • Early warning of issues
  • Honest and transparent

Meeting Expectations:

  • Timely information submission
  • Accurate financial statements
  • Professional presentation
  • Consistent performance

What Sureties Want to See

Growing contractors should demonstrate:

  • Improving financial metrics
  • Successful project completions
  • Controlled growth rate
  • Strong management team
  • Professional operations

Common Bonding Challenges

Challenge 1: Insufficient Capital

Problem: Working capital limits bonding capacity.

Solutions:

  • Retain more earnings
  • Secure line of credit
  • Reduce debt
  • Consider equity investment

Challenge 2: Limited Experience

Problem: Lack of relevant project history.

Solutions:

  • Build experience gradually
  • Partner with experienced firms
  • Document all project experience
  • Develop key personnel

Challenge 3: Financial Statement Quality

Problem: Statements don't meet surety standards.

Solutions:

  • Use construction-specialized CPA
  • Upgrade to reviewed/audited
  • Improve financial reporting
  • Provide detailed WIP schedules

Challenge 4: Claims History

Problem: Past claims damage bonding prospects.

Solutions:

  • Document claim circumstances
  • Show corrective actions taken
  • Demonstrate improved performance
  • Consider alternative sureties

Next Steps

Ready to strengthen your bonding position?

  1. Assess your current capacity - Understand your limits
  2. Review financials - Identify improvement areas
  3. Build relationships - Connect with surety partners
  4. Document experience - Maintain comprehensive records
  5. Plan growth - Align project pursuit with capacity

Related Articles

Frequently Asked Questions

What's the difference between bonding capacity and credit? Bonding capacity is the maximum value of bonded contracts you can have outstanding. It's based on financial strength and experience, not borrowed money.

Can I get bonds with bad credit? Personal credit matters, but business financials are more important. Work with a bond producer experienced in placing accounts with credit challenges.

How quickly can I get a performance bond? With an established bonding relationship, bonds can be issued in 24-48 hours. New relationships take 2-4 weeks for underwriting.

What happens if I can't finish a bonded project? Communicate with your surety immediately. They may provide financial or technical assistance to help you complete. Default triggers serious consequences.

Do I need a bond for every project? Not always. Many private projects don't require bonds. Public works usually do. Review contract requirements carefully.

ConstructionBids.ai LogoConstructionBids.ai

AI-powered construction bid discovery platform. Find government and private opportunities from 2,000+ sources across all 50 states.

support@constructionbids.ai

Disclaimer: ConstructionBids.ai aggregates publicly available bid information from government sources. While we strive to provide accurate and up-to-date information, we do not guarantee the accuracy, completeness, or timeliness of any bid data. Users should verify all information with the original source before making business decisions. ConstructionBids.ai is not affiliated with any government agency.

Data Sources: Bid opportunities are sourced from federal, state, county, and municipal government portals including but not limited to SAM.gov, state procurement websites, and local government bid boards. All data remains the property of the respective government entities.

© 2025 ConstructionBids.ai. All rights reserved.
Made in the USAPrivacyTerms